The 12–16 week New Hampshire ADU build, week by week
12 to 16 weeks, sitework to keys.
Once your permit's in hand and we move the machines to your site, the build runs the same calendar every time — ground-breaking to the day you hand keys to a tenant.
Heads up on timing: lead time to pouring a foundation is currently about 6 months — that covers design, permitting, and your spot in the build queue. The 12–16 week clock below starts the day the permit is in hand and we break ground.
- Wk 1–3Step 1Sitework + foundation
Permit in hand, we move the machines to your site. Clearing, excavation, and the foundation poured to spec. Water, sewer, electric, and data trenched from your house to the new pad.
- Wk 4–7Step 2Set + weather-tight
Your ADU is set on the foundation. Roof tied in, exterior weather-sealed, utilities connected. From the outside it looks done.
- Wk 8–13Step 3Interior finish
Electrical and plumbing finished out. Flooring, fixtures, cabinets, paint, appliances. Walk-through with you for any punch-list items.
- Wk 14–16Step 4Inspection + keys
Town final inspection. Certificate of Occupancy issued. Keys handed over — you can have a tenant in by the end of the week.